Wednesday, July 14, 2010

Friday, July 9, 2010










Pouring footing, stub wall near line "E", slab in crawl space, and foundation wall on lake side. Drainage trench has been dug passing on the lake side and into the trees which will carry French drain water (there was no drain on the lake side and the one at the back was inadequate).

Thursday, July 8, 2010

Tuesday, July 6, 2010

Excavation






Oil tanks are gone. Down to grade at NW corner. Digging for drainage toward the lake.